4th September 2007
The first Autumn month arrived and of course the weather changed straightway.
Now is quite cold , about 15 C and is very cloudy . The last few days was raining .
Up in Beli Iskar and Eagle Rock is sunny.
The Complex is near completion .
Wing C is ready, in few apartments the furniture needs to be completed, all te kitchens are done, everything is on place, the wing is clean.
In wing B carpenters are fitting the doors and the kitchens. Laminate parquet is fitting at the moment, painting of the apartments is continuing.
In wing A the doors are mounting, tiling the terraces with granite tiles is continuing.
The Spa Center is ready for the company , which is going to do the pool, the sauna, Jacuzzi, steam room.
Outside of wing C plastering on the top of the thermo insulation is almost finishing.
The builders has started to do the alleys in front of the complex, because the gardeners are coming in few days.
The workers are mounting the railings of the staircases outside.