4th October 2006
October is one of the favourite autumn month around here, because the weather is very sunny and quite.
In Beli Iskar the work in the Complex is going well and in the normal way.
Rendering and plastering in wing C is continuing and the electricians finished mounting all the wires on the fifth floor. Seven bathrooms are tiled in this wing and the tillers are continuing the next bathrooms in the same wing.
The workers are building the apartments on the third floor in wing B.
In wing A builders are preparing the work - shuttering and framework for the first slab of level +/- 0,00.