6th November 2006
Wing A - In wing A half of the apartments on the Ground floor are ready and the builders are working on the rest of them building the rest
Water - Main installation in the underground floor is ready
The work in this wing now is concentrate for the building of the new apartments
Wing B - Finishing of the maisonettes
- Water-main installation of the I, II and II floors is ready
- The electricity installation on the I and II floor is ready and they will continuing with the next one
In this wing the work at the moment is concentrate again of finishing jobs in the apartments - building the walls between the apartments and rendering inside.
In wing C - Tiling the bathrooms with Savana blue tiles and mounting the water heaters in the bathrooms. Also inside plastering of the walls, plastering of the walls with gypsum cardboard , bordering of the edges of the roof with wood, mounting the guttering and mounting PVC windows.