In wing A today the guys from the company which are fitting the PVC joinery are mounted the aluminum netting for the windows. On the ground floor the water main pipes are fitted as well. The masonry of the other apartments on the next floors in this wing is continuing.
In wing C fitting the doors of the apartments is the main job now.
Most of the apartments are painted and on the last floor the apartments has the lights as well.
The weather is not very cold during the day, but early in the morning and in the afternoons is very cold.