7th March 2007
The work in the complex is going in the usual way. The snow is gone and the probably is not going to have any more for this year.
The main work now is concentrate in wing A, because wing C is almost ready.
In wing A the apartments on the first and second floor are separated now and plastered with gypsum cardboard and, builders are making the fine plaster on the walls inside the apartments.
The water –main installation and the electricity installation are done on these two floors.
On the third floor the water –main installation is ready and in few days the electricians will start working there. All the windows are fitted.
On the last floor the tower is getting her shape and the next step on this floor is to start separating the apartments.
In wing B the windows are fitted, the water and electricity installations are done and all the bathrooms are tiled .Now the builders are plastering the apartments with fine plaster inside. Also in this wing the outside thermo insulation is has been done and plastered outside.