8th May 2007
From a few days ago the company which is going to fit all the internal railings in the Complex is working there.
In wing C the main railing is fitted, but this is not the final shape. The metal construction is going to be painted and fitted wooden handle on the top.
Few pictures are showing the railings on the terraces which the carpenters are mounting at the moment in wing C.
In wing B on the whole reception area the builders are starting to prepare the walls for the gypsum plaster boards, they are mounting the aluminum construction on the walls.
In wing A the outside thermo insulation is still continuing.
New asphalt pavement is going to be made on the main road to Borovets , where Eagle Rock is situated.