10th April 2007
Happy Easter!
The work in the Complex stopped just for one day - for the Easter holiday and now is continuing in the usual way.
In wing A the roof is done, the last floor is almost done , but it will take few more days to finish plastering with gypsum plaster boards the walls of the apartments.
In the floors bellow the workers are doing the bathrooms and plastering the walls.
Wing B - finishing the apartments with gypsum plaster boards and working on the inner staircases in the maisonettes.
Wing A - plastering the facade with stone tiles , fitting the railings and tiling the corridors in the apartments on the ground floor.
The weather is nice and sunny, but in the mountain still has snow , the runs are good for skiing.