10th October 2006
In wing A the swimming pool has been found and the builders are doing the paths around it. The builders are finishing the shuttering of level 0.00 and they will start the fixture after that, because by the end of the week the first slab of level 0.00 will be make.
In wing B the masonry of the dividing walls on the second floor is continuing at the moment . The shuttering for the third slab is almost ready and they will start the fixture, because after 7-8 days this slab is going to be make as well.
The electricians are on the first floor at the moment, because all the wires and installation are in place on the ground floor.
In wing C on the first floor all the bathrooms which have Krisi beige are ready, and the guys are tiling the bathrooms on the second and the third floor.
The plastering in this wing is still continuing and specially around all the new windows.
Plastering of the wall on the third floor is almost finished.
From a few days in wing C the outside thermo insulation has been started and the builders will continuing with that until the weather is good for this job.
The electricity installation and water - main installation are ready in this wing.