14th March 2007
The work in the Complex is going in the usual way.
In wing C the electricians will finish the second floor today and they will move to the next floor from tomorrow.
On the third floor separating the apartments is the job which the builders are doing now.
At the same time on the floors bellow plastering the walls of the apartments and in the bathrooms with gypsum plaster boards is continuing.
In wing B the builders are plastering the corridors with cement plaster and also plastering the apartments with gypsum plaster boards.
In wing C workers are doing some finishing work – finishing the plinths of the terracotta tiles in the corridors, fitting the borders of the doors, plastering around the doors and the windows where is needed.