17th April 2007
In wing A the builders are doing the water-main installation and the electrical installation on the last floor. Tiling of the bathrooms in this wing still continuing.
Plastering with gypsum plaster boards continuing as well.
In wing B the outside thermo insulation is still continuing, plastering the apartments with gypsum plaster boards is the other main job in this wing. Few bathrooms are going to be finished in this wing and in the near two - three days all the bathrooms will be ready.
In wing C the builders are mainly working some finishing touches in the apartments and preparing the wing for painting.
The railings of the staircase in this wing are ready and they will be fitted in the coming days.
The other good thing is that in the village of Beli Iskar new pavements are going to be made, the workers already started from the beginning of the village on the main street.