19th February 2007
From a few days we have a lot of snow, but is not very cold and is very good for skiing and of course all the tourist are very happy.
The work in the Complex is continuing . In wing C the builders are leveling and tiling the staircases and they are finishing tiling the corridors and the entrances of the of the apartments .
In wing B the main job now is concentrate in the bathrooms and plastering the walls with gypsum cardboard. The electricity and the water main installation are ready.
On the ground and the first floor in wing C separating the apartments is done , some of the windows are fitted and the outside thermo insulation has been started.
Some pictures from today are from the spa area - the swimming pools and the other spa rooms , which are in the basment floor of wing C.