19th June 2007
The Summer finally came to us and is no more rain and gray sky!
The temperatures are around 29 C and the mountain is green and beautiful!
In Eagle Rock the work going as usual.
Outside the builders are continuing the foundation of the fence around the Complex.
In wing A the builders are doing the thermo insulation of the west site and at the same time tiling of the façade with stone tiles is continuing.
From few days the builders are fitting the gutters of the wing C and painting the facade with the special white paint is continuing.
In wing A all the bathrooms are done, all the ceilings are done, all the corridors and apartments are has been paneled with gypsum plaster boards and plastered on the top.
At the moment the builders are tiling the terraces from the top floor with granite tiles.
In wing B the ceilings and corridors floors are has been done except the ground floor.
The builders are working on this floor at the moment. The bathrooms and the terraces are done as well.
Painting of the apartments and corridors in wing C is continuing.
In the SPA center , in wing A, the builders has started plastered the walls and the ventilation system is under construction now.