19th October 2006
First snow arrived in Rila Mountain before three days.
The runs in Borovets are covered with tiny layer of snow.
The temperatures in the morning are under zero, but during the day they are raising up.
The work in the Complex is going well.
From two days builders has started working on the roof in the south wing C - they are making first thermo insulation and then they will continuing with the other things.
The electricians has finished the fifth floor and rendering and plastering is still continuing in this wing. Plastering outside the building has been started from a few days.
The third slab in wing B is ready and dividing the apartments on the third floor is almost ready as well.
Following slab in wing B is going to be make next week. At the moment the builders are doing the framework for the slab.
The last pictures from today are from the Archeological object -" Shishmanovo kale " from IV - VI century , found before two years ago, this is a town of the Middle Ages. It is located two kilometers away from Beli Iskar , on the right hand site on the road Samokov - Beli Iskar. The whole hill is under the archeological excavation . The project is sponsored from the Municipality of Samokov and one one of the purposes of this Project is to make this place tourist destination. Very soon the town Museum will have English speaking guide. More information abot this project will be replaced soon.
If you want to see all the pictures please press the link bellow.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|