21 March 2007
Today it is raining, but not cold and the builders are working inside.
For today the outside work has stopped until the weather is getting better. From tomorrow the sun is coming again and the work will continue.
From two days the specialist of facade tiling with stone tiles are in the Complex and they have started the first wall.
On wing B making the outside thermo insulation is the main job for the moment.
In wing A only the last floor is not ready with separating of the apartments. Making the rough plaster on the floor is ready and when the plaster is dry the guys which are working on the apartments will come to this floor.
On the first and second floor plastering with gypsum plaster boards is done, the electricians are ready and the water–main installation is done. Today and tomorrow the electricians will finish on the third floor. And they will move to the last one.
The fine finishing work in wing C is continuing.