24th November 2006
Today 24th of November the autumn doesn`t want to go way, which
is very good for us, because the work in the Complex is going with
full power.
In the beginning of December the weather will change
slightly and is good if we could finished as much job as we can.
In wing A the Ground and the First Floor are ready
and tomorrow the first slab on the second floor is going to be make.
In wing B the shuttering for the roof slab is preparing
at the moment and within a week this slab is going to be done as
well.
In wing C plastering with gypsum cardboard in the corridors
and the apartments, tiling the bathrooms, thermo insulation outside
, making the false ceiling and covering the roof with bitumen roof
tiles is continuing.