27th March 2007
The weather is not very nice and we are having snow. The tempratures are minus zero in the mornings.
In Borovets is still good for skiing, because a few days ago it was snowing a lot.
But the work in the Complex is going in the normal way.
In wing A the electricians have finished the third floor and they will move to the last one.
In the area , where is the Spa center, the builders are doing it the “english yard” windows.
The bathrooms on the first and second floor are almost ready.
In wing B plastering with gypsum plasterboards is continuing.
The cave of the lift in the reception area has been made today as well.
In wing C the builders are tiling the balconies, fitting the borders of the doors and plastering around them is still continuing.