29th June 2007
Tomorrow – 30.06.2007 is the Rilski Zelnik Festival in Beli Iskar and many guests are already in the village. The guests will have the chance to taste the famous "Rilski zelnik" (special kind of pastry). The biggest event of the Festival, very appropriately, is the contest for the tastiest "zelnik".
You can see the pictures here
The work in the Complex is going well, the weather is not as hot as was last week and now everybody are feeling better.
The builders are continuing with the fence around the Complex and they have started leveling the place from today.
The second tower is under construction now and when is ready both towers will be lift it up with the crane to the top.
Painting the façade of wing C is continuing.
From Monday the carpenters has started mounting the kitchens in wing C.
They have started from the top floor, because the painters are finishing the floors bellow and in few apartment on the ground floor tiling with laminate parquet is continuing...
In wing B, the carpenters are mounting the internal and main doors of the apartments.
In wing A fitting of the PVC windows of the corner apartments is has been started from few days ago.
The main job in this wing is concentrate now in the Spa center – plastering the walls, making the inner brick walls, fitting the pipes of the ventilation system. The company, specialize of constructing the pools will start the work soon and we need to prepare the place for them...